Electrical Load Calculation for Residential and Commercial Buildings

Written ByPriyanka
Published dateNov 28
Read time9 min

Electrical load calculation for residential and commercial buildings is the job of working out how much power a building will really draw at its busiest moment, so the cables, breakers, transformer and DG set can be sized to match. Not the sum of everything installed. The realistic peak.

Get that number right and the rest of your MEP design falls into place. Get it wrong and you either buy a transformer twice the size you need, or you stand in a basement substation in May wondering why the main breaker keeps tripping. India has been testing this lately. On 21 May 2026, peak demand touched a record 270.82 GW, up from the 250 GW record of May 2024, according to the Ministry of Power. A big slice of that is air conditioners, and every one of them started life as a line in somebody's load schedule.

So here's the method the way you'd use it on a project. Connected load, demand and diversity factors, the load schedule, the steps, then a worked example for one flat and a 40-flat building. After that, what changes for commercial buildings and how to get from kW to a transformer size. Once you have your maximum demand, the next job is sizing the feeders that carry it, and our cable sizing calculation guide works through current rating, derating and voltage drop step by step. Load estimation is also the first step of the wider electrical design for buildings process.

Connected Load vs Maximum Demand

Connected load is the total rating of everything installed. Maximum demand is the most the building will draw at one time. Maximum demand is always the smaller number, and it's the one that sizes your equipment.

Picture a 3BHK flat in Pune. Three split ACs, two geysers, eight fans, a kitchen full of mixers and microwaves. Add up the nameplates and you land near 14 kW. Now think of 7 pm on a May evening: two ACs running, one geyser on, the fridge humming, lights on. The flat is nowhere near 14 kW. It's closer to 8.

Cooling is why Indian homes behave like this. A 2024 household survey by CLASP and the Bureau of Energy Efficiency, covering 4,321 households across 20 states, found that fans, ACs and coolers now account for about 40% of residential electricity use. So the AC pattern decides most of a building's peak. The real question isn't "what's installed?" but "what runs at the same time?"

Size from connected load and you pay for capacity that never gets used. In the worked example below, one building has 607 kW connected and about 266 kW of maximum demand. That gap is where the money sits.

Demand Factor vs Diversity Factor (Definitions and Formulas)

Demand factor trims one group of loads. Diversity factor recognises that different groups peak at different times. Two ideas, easy to mix up.

Demand factor = Maximum demand ÷ Connected load

So: Maximum demand = Connected load × Demand factor

It's 1 or less. Shop lighting runs all day, so its factor sits near 1. Sockets, geysers and washing machines sit much lower, because they're rarely all on together.

Diversity factor = Sum of individual maximum demands ÷ Maximum demand of the combined system

It's 1 or more. Forty flats might each peak at around 7.8 kW, but they won't all peak in the same minute.

One thing trips people up. Some textbooks define diversity factor as a number above 1. Many design tables, including the IEC-based ones for apartment blocks, print a multiplier below 1 instead. They're reciprocals: a multiplier of 0.75 is a diversity factor of 1.33. This post uses the multiplier, because that's the form you'll meet in tables.

Where do the actual percentages come from? The code and the supply authority. NBC 2016 Part 8 (Building Services) and IS 732 set the framework for electrical installations in India. But the DISCOM sanctions your load, so its norms win wherever they differ. Don't lift factors from a random PDF and call it design.


Want to build load schedules like this on real building projects? Kaarwan's BIM Certification for MEP Engineers walks you through electrical design with live mentors.

Inputs: The Load Schedule

A load schedule is a table of every load in the building, with rating, quantity, phase and category. Everything else is built on top of it. If it's wrong or stale, so is your transformer.

Each row needs a description, quantity, rating (W or kW), voltage and phase, a category (lighting, fans, sockets, kitchen, HVAC, motors, lifts, pumps), a demand factor and the resulting demand. Keep it in one spreadsheet and update it through every stage of the MEP design process. HVAC and pump selections will change. They always do.

Read nameplates wherever you can. Where equipment isn't chosen yet, utility calculators publish usable ranges. The Mahavitaran load calculator is a handy way to cross-check a home. For lighting, take the fixture count from the lighting design rather than guessing, and our lighting design basics on lux levels and fixture layout shows how those numbers come about.

LoadTypical rating
LED bulb or tube light10–20 W
Ceiling or table fan40–75 W
Refrigerator150–400 W
Washing machine300–500 W
Microwave, mixer, iron750–1,500 W
Water pump (1 HP)750–1,000 W
Geyser2,000–3,000 W
1.5 ton split AC1,500–2,200 W

Motors are rated in HP. Use 1 HP ≈ 746 W, then allow for motor efficiency, because the input power is higher than the shaft output.

Step-by-Step Method

  1. List every load by category. Lighting, fans, sockets, kitchen, HVAC, motors, lifts, pumps.
  2. Add up the connected load. Quantity × rating for each row, converted to kW.
  3. Apply demand factors, group by group. ACs and geysers get lower factors than a fridge that never switches off.
  4. Apply diversity between flats, floors or panels. Once. Apply it at the panel and again at the main board and you'll undersize the service.
  5. Convert to kVA and current. kVA = kW ÷ power factor. Single-phase current: I = P ÷ (V × PF), with V about 230. Three-phase current: I = P ÷ (√3 × V × PF), with V about 415.
  6. Add 20–25% spare, then pick the next standard size up.

Worked Example: One Apartment, Then a 40-Flat Building

The numbers below are illustrative. Real factors come from your design basis and your DISCOM.

One 3BHK flat

LoadConnected (W)Demand factorDemand (W)
Lighting (25 LEDs × 12 W)3000.8240
Fans (8 × 70 W)5600.8448
Plug points (TV, PC, chargers)6000.5300
Refrigerator3001.0300
Kitchen (microwave, mixer, toaster)2,5000.41,000
Washing machine5000.5250
Geysers (2 × 2,000 W)4,0000.52,000
Split ACs (3 × 1,800 W)5,4000.63,240
Total14,1607,778

Connected load is 14.16 kW. Maximum demand is 7.78 kW, about 55% of it, which sits comfortably inside the 0.4–0.7 range usually seen for homes. At a power factor of 0.9 that's 8.64 kVA.

Current comes to about 37.6 A on a single-phase 230 V supply, or about 12 A per phase on three-phase 415 V. Single-phase limits differ from one DISCOM to another, so check what yours allows before you pick the connection.

The 40-flat building

Step A: flats. Forty flats at 7.78 kW is 311.1 kW if they all peaked together. They won't. Take a diversity multiplier of 0.75 (a diversity factor of 1.33) and the flats come to about 233.3 kW.

As a sanity check, the IEC-based apartment-block table gives 0.41 on connected load for 40–49 flats. On our 566.4 kW of connected flat load, that's about 232 kW. The two routes land within 1% of each other.

Step B: common areas.

LoadConnected (kW)BasisDemand (kW)
Lifts (2 × 7.5 kW)15.0Largest 100%, next 75%13.1
Domestic water pumps (2 × 3.7 kW, one standby)7.4One running3.7
Common lighting (stairs, lobbies, stilt, external)10.00.99.0
Basement ventilation and misc.8.00.86.4
Total40.432.2

Step C: the building.

BlockConnected (kW)Maximum demand (kW)
40 flats566.4233.3
Common areas40.432.2
Building total606.8265.5

Maximum demand is about 44% of connected load. At a power factor of 0.9, that's 295 kVA. Add 20% spare and you get 354 kVA, which points to a 400 kVA transformer. A 400 kVA unit carries about 557 A on the 415 V side, so you'd look at a 630 A incomer.

Now the mistake. Size from connected load and you get 606.8 ÷ 0.9 = 674 kVA, which means an 800 kVA transformer. That's double the capacity, plus the switchgear, cables and plinth space to match. Fire pumps aren't in the running demand above. They go into the essential-load list when you size the DG set.

Practise load calculations on real projects in the MEP design course.


Tired of load schedules that fall apart at coordination stage? Learn the MEP workflow, load estimates to single line diagrams, in Kaarwan's MEP BIM certification.

Commercial Buildings: What Changes (HVAC, Lifts, Pumps)

The method stays the same. What changes is the size of the loads, who owns them, and when they peak.

ResidentialCommercial
PeakEvening, when ACs, geysers and cooking overlapAfternoon, through working hours
Biggest loadACs and geysersChillers, VRF or AHUs
DiversityAggressive, many similar flatsGentler, long operating hours
Special loadsWater pumps, a couple of liftsLifts, fire pumps, IT and UPS, EV chargers, kitchens

The Ministry of Power says national peak demand usually falls between 2 pm and 4 pm. That's exactly when offices and malls are running flat out.

HVAC. Plant is rated in tons of refrigeration, and 1 TR is about 3.517 kW of cooling. That's cooling, not electrical input. A 100 TR plant delivers roughly 352 kW of cooling and draws far less than that electrically. Take the electrical rating from the equipment data and tie it to your heat load calculation.

Lifts and pumps. Take the largest lift motor at full value and the next at around 75%. For pumps, count only the duty pumps, not the standby.

Mixed use. A retail podium and an office tower above it don't peak together. Retail leans toward evenings, offices toward afternoons. That's real diversity, so work out coincident peaks floor by floor.

Tenant and landlord loads. Keep them on separate lines. EV chargers and server rooms get their own rows too. They're not rounding errors.

From kW to kVA: Power Factor and Transformer Sizing

kVA = kW ÷ power factor. Transformers and DG sets are rated in kVA because they have to carry current, not just real power. A low power factor means more current for the same kW. For building demand, designers usually take 0.85–0.9.

Check how your DISCOM bills. Where billing is on kVA or kVAh, a low power factor goes straight into the bill, and APFC panels start paying for themselves.

For the transformer: take maximum demand in kW, divide by power factor, add 20–25% for growth, then pick the next standard rating up (315, 400, 500, 630, 800 kVA and so on). Your 295 kVA becomes 354, which becomes 400. Check the utility's connection rules before you freeze it.

The DG set is a different job. Size it on the essential loads only, such as one lift, fire pumps, common lighting and water pumps, and check motor starting. Your single line diagram and your MEP drawings should show which board carries what.

Common Mistakes

  • Sizing from connected load. The 800 kVA mistake above.
  • Applying diversity twice. Once at the panel and again at the main board. The service ends up undersized.
  • Guessing socket loads. A 5 A socket point isn't a 1.1 kW load running all day.
  • Forgetting common-area loads. Lifts, pumps, basement ventilation and external lighting add up fast.
  • Mixing up kW and kVA. They're different numbers. Power factor is the bridge.
  • Letting the schedule go stale. HVAC changes, the load schedule doesn't, and the error shows up at coordination stage.

If you're moving from site work into design, this 6-month plan from site electrical engineer to electrical design engineer lays out how to make the switch.

FAQs

What is connected load?

Connected load is the total rated power of every light, fan, socket, motor and appliance installed in a building, added up at nameplate value, in watts or kW. It shows what is installed, not what runs together. A 14 kW flat might draw only 8 kW at its peak.

What is the difference between demand factor and diversity factor?

Demand factor is maximum demand divided by connected load for one group of loads, so it is always 1 or less. Diversity factor is the sum of individual maximum demands divided by the combined maximum demand, so it is 1 or more. Some tables print its reciprocal as a multiplier below 1.

How do you calculate maximum demand?

List every load with its connected rating, multiply each group by its demand factor, then add the results. For several flats, floors or panels, apply a diversity multiplier on top. Convert the total to kVA using power factor. Check your DISCOM's norms and NBC 2016 values before finalising.

How do you convert kW to kVA?

Divide kW by the power factor: kVA = kW ÷ PF. For building demand, designers usually take a power factor of 0.85 to 0.9. So 265 kW at 0.9 is about 294 kVA. Always size transformers and DG sets in kVA, not kW.

How is transformer size calculated for a building?

Take the building's maximum demand in kW, divide by power factor to get kVA, add 20–25% for growth, then pick the next standard rating above it. A 295 kVA demand with 20% spare gives about 354 kVA, so a 400 kVA transformer. Check the utility's rules too.

Chat with us

Get the syllabus

View Course

Get the syllabus

View Course
curriculum-background
Phone
curriculum-background

₹3500 first call is on us 🎉

Schedule 1:1 free counselling.

  • Tailored Guidance for Your Success
  • Gain Real-World Insights
  • Life-Changing Conversation
Phone
By submitting, you agree to Kaarwan's Terms and Privacy policy

Get the syllabus

View Course

Get the syllabus

View Course
curriculum-background
Phone
curriculum-background
user-group
Not sure which skills lead to high-paying jobs?Get expert career guidance
Phone
Chat with Uswhatsapp
Priyanka

Priyanka

I’m Priyanka Choudhary, a content writer passionate about architecture, design, and turning complex ideas into clear, engaging stories.

Disclaimer: Views are the author's own and provided "as is" strictly for informational purposes. Kaarwan expressly disclaims all liability for any errors, omissions, or damages arising from this content. For corrections: hola@kaarwan.com.